LVT Number: #29785

Landlord applied for MCI rent hikes based on rewiring, installation of new walls in the building's switch gear room, new hallway facias and case enclosures, as well as foundation reinforcement and steel support installations related to the rewiring. The DRA ruled for landlord in part, but disallowed costs related to mobilization, professional consulting fees, and a few other items. Landlord appealed and won, in part.

Full Article Access:

Full access to complete articles from Landlord v. Tenant is for subscribers only.

Not yet ready to subscribe?

SP 10 Downing LLC: DHCR Adm. Rev. Docket No. AU430012RO (9/7/18) [3-pg. doc.]